What Is a Data Center?
Understanding Data Centers in Wyoming
A data center is a facility built to house computer servers, storage systems, and networking equipment used to store, process, and move digital information.
Wyoming's Legal Definition
For tax purposes, Wyoming defines a “data processing services center” as a business that mainly provides space and infrastructure to house networked servers and their storage in one location. (Source: Wyoming Statute 39-15-101(a)(xliv))
​
This definition is the basis for the state’s sales tax exemption on qualifying data center equipment. To qualify, a facility has to invest at least $2 million in equipment, on top of a large investment in the building itself. See “Do data centers get tax breaks?” below for details (Wyoming Legislature).
This page covers facilities that store, process and move data for businesses and online services. It does not include cryptocurrency mining operations.
​
How Local Communities Define It
Individual communities may define data centers differently for local planning purposes. Cheyenne adopted its own zoning definition in 2022 covering buildings designed to house networked computer and data processing equipment, along with related support infrastructure. (Source: City of Cheyenne, Planning and Development Department)
​
Small to Hyperscale: A Matter of Size
Data centers range widely in size — from small operations under 5,000 square feet to large "hyperscale" facilities, generally defined as at least 5,000 servers and more than 10,000 square feet. (Source: City of Cheyenne, citing IBM and CoreSite)

Nearly Two Decades of Data Centers in Wyoming
Wyoming has been home to data centers since 2007. This timeline follows each facility from the day it was announced and notes where it stands today. Every entry links to its original source.
Operating — Open and running
Planned — Announced or approved, not yet under construction
Under Construction — Work is underway
Who Decides What
No single agency approves a data center in Wyoming. Depending on location and size, a project may need approval from a city, a county and the state. Here's who decides what, and where to follow along.
City Councils — Annexation and zoning inside city limits. Cheyenne agendas and minutes.
County Commissions — Zoning and conditional use permits outside city limits. Laramie County meetings.
Wyoming DEQ Air Quality — Permits for generators and on-site power, with public comment periods. Search permits
Industrial Siting Council — State review of large industrial projects. Projects in designated industrial parks are exempt. Requirements and decisions.
Public Service Commission — Approves utility rates and tariffs, including how data centers pay for power. Dockets and filings.
Governor's Office — Executive Order 2026-03 sets statewide principles for how agencies review data center projects. Executive orders.

What This Page Covers
Because of their scale, these facilities intersect with a community in several ways at once: local economies, natural resources, and community infrastructure. This page organizes what is publicly known into three areas — Economic, Environmental, and Community — with the source cited alongside each figure or claim. It will be updated as new, verified information becomes available.
Economic
Facts
About our local and state taxes
-
In 2022, Cheyenne's effective property tax rate was about 0.65% (Wyoming Legislature).
-
This increase is caused by the increase in housing and living costs along with the increase in affordable living demand.
-
Pandemic-era housing demand and low mortgage rates drove property values up across Wyoming (Cowboy State Daily).
-
-
Datacenters are also paying these increased taxes.
-
They pay in full for property and land tax.
-
Wyoming's sales tax exemption for data center equipment does not cover property taxes (Wyoming Tribune Eagle).
-
-
Black Hills Energy established a Tariff.
-
This tariff means that citizens and communities are not footing or paying the bill when it comes to datacenters and their development.
-
From sound to wildlife habitat, data centers are required to operate within specific environmental limits. Here's what those limits are and how they're enforced.
Environmental
Data centers affect the land, water, and electricity around them. This section covers all three: Nature (noise, air quality, and wildlife impact), Water (how much data centers use and the technology behind it), and Electricity (power draw and what it costs to serve large facilities) — with sourced facts for each.
From sound to wildlife habitat, data centers are required to operate within specific environmental limits. Here's what those limits are and how they're enforced.
Cheyenne law sets hard limits on how much sound a data center can produce at its property line (City of Cheyenne Planning & Development, Aug. 2025).
If a facility exceeds these limits, it's no longer classified as a data center under city code — it's reclassified as an industrial use, which comes with stricter oversight. A sound study has to prove a project will meet these limits before it can be approved.
(Source: City of Cheyenne Planning & Development, Aug. 2025)
​
What data center operators say about noise:
-
Microsoft states its servers run inside sealed buildings and aren't audible from outside, backup generators run only for brief periodic testing, and outdoor cooling equipment is engineered with sound-dampening measures to stay within local limits — consistent with the City's property-line standard above. (Source: Microsoft Noise Fact Sheet)
-
Meta has not published noise-specific information for their Cheyenne facility.
-
Google's Laramie County campus is planned and not yet built. No noise-specific information has been published for it yet.
-
Other Cheyenne-area operators (Lunavi, Related Digital, Vantage) — no publicly available noise-specific information found.
Community & Civic Investments
Data center operators in Cheyenne and Laramie County contribute to local public services through off-site infrastructure funding, educational partnerships, and grant programs.
$68M+
In local municipal & roadway upgrades

Image Credits: Matthew Idler Photography
-
Microsoft reports committing more than $68 million toward completed and planned off-site infrastructure supporting its Cheyenne facilities, covering roadways, storm sewers, water mains, and greenways.
-
(Note: Specific off-site utility obligations are governed across individual site-development agreements rather than a single municipal community benefits agreement.)
-
​
“Microsoft has committed over $68M in completed and future off-site infrastructure improvements across Cheyenne. Projects like roadway and storm sewer improvements, trail roadway and greenway improvements, new pump stations, and improved municipal water infrastructure are critical for datacenter operation, but they also make up the infrastructure systems that Cheyenne residents use every day.” -Microsoft Source, April 14, 2026

Contact the Data Centers
Microsoft
Email: CheyenneDC@microsoft.com
Phone: 307-823-6336
Meta
Email: commdev@meta.com
Questions We’ve Heard, Answers We’ve Found
Will data centers raise my electric bill?
Black Hills Energy, Cheyenne’s electric company, says no.
​
Data centers here pay a separate rate. Under it, they pay for the power lines and equipment needed to serve them, so those costs aren’t passed on to your bill (Black Hills Energy presentation to the Wyoming Legislature).
Your bill can still go up for other reasons, like upgrades to the power system everyone uses. Before Black Hills can raise rates, the Wyoming Public Service Commission has to approve it, and the public can comment first (Wyoming PSC).
​
For more on how data centers buy power, see the Electricity section above.
How much water do data centers use?
It depends on how each one is cooled (Congressional Research Service).
-
Water withdrawn (often just called “water use”) is water taken in. Much of it can be treated and returned to rivers, lakes or groundwater.
-
Water consumed is the part that isn’t returned, mostly lost to evaporation (USGS).
Closed-loop cooling reuses the same water in sealed pipes, topped off every few years. Meta says its Cheyenne facility is designed to use zero operational water this way (Meta).
​
Evaporative cooling evaporates water to cool equipment. Microsoft says it uses this less than 10% of the year, and what doesn’t evaporate goes to Cheyenne’s wastewater plant (Microsoft).
​
Air-cooled, closed-loop cooling uses air instead of water. Google says its planned Laramie County campus will use this system, plus 20–30 million gallons a year for restrooms, kitchens and fire suppression (Wyoming Tribune Eagle).
​
We didn’t find a statewide total. Cheyenne is the one community we found that publishes numbers: the city reports its data centers used about 93 million gallons in 2025, roughly 2% of the city’s water (City of Cheyenne: see “How are we monitoring data center water usage?”).
Questions about your local water supply go to your water utility. In Cheyenne, that’s BOPU. More detail is in the Water tab of the Environmental section.
Are data centers loud?
In Cheyenne, data centers have to stay within noise limits measured at their property line (City of Cheyenne):
-
Next to homes and most other areas: 60 decibels during the day and 55 at night.
-
Next to commercial or industrial areas: 70 decibels during the day and 65 at night.
Before a project is approved, a sound study has to show it will meet those limits. A facility that goes over them is no longer treated as a data center under city code. It’s reclassified as industrial, which comes with stricter rules.
Microsoft says its servers run inside sealed buildings and can’t be heard outside, and that its backup generators only run for brief testing (Microsoft).
Noise rules outside Cheyenne are set by each city or county. If you have a noise concern about a facility in Cheyenne, contact the City of Cheyenne at (307) 637-6200. More detail is in the Noise tab of the Environmental section.
Do the backup generators cause air or noise pollution?
Data centers keep diesel generators on site as backup power in case the grid goes down. Like any diesel engine, they release air pollution and make noise when they run.
​
Air: In Wyoming, these generators and their fuel tanks need an air quality permit from the Department of Environmental Quality (DEQ) before they can be installed (Wyoming DEQ). Before DEQ approves a permit, it posts a public notice and opens a comment period. A public hearing is held if a formally affected party requests one.
​
Noise: Microsoft says its generators only run for brief periodic testing (Microsoft). In Cheyenne, data centers must also stay within the city’s noise limits at their property line. See “Are data centers loud?” above.
​
For example, Microsoft’s Cheyenne data centers have DEQ approval for 128 backup generators. Google said in September that it planned to apply for a generator permit for its Laramie County campus, which would open a 30-day public comment period (Wyoming Tribune Eagle).
​
Permits are public. You can look up any permitted facility in Wyoming for free at openair.wyo.gov. The Air tab in the Environmental section walks through how.
Who decides whether a data center gets built?
It depends on where it’s built. Several local and state groups each review a different part:
-
City council: zoning and annexation for projects inside city limits.
-
County commission: zoning and permits for projects outside city limits.
-
Wyoming DEQ: air quality permits for backup generators.
-
Industrial Siting Council: state review of large industrial projects, except those in designated industrial parks (Wyoming DEQ).
-
Public Service Commission: utility rates, including how data centers pay for power (Wyoming PSC).
-
Governor’s Office: Executive Order 2026-03 sets statewide principles for how agencies review data center projects (Governor’s Office).
Links to each are in the Who Decides What section near the top of the page.
How can I share my opinion on a proposed data center?
You can speak up at several points before a project is approved:
-
City council or county commission meetings include public comment, and agendas are posted ahead of time. Check your city or county website to see when a project is on the agenda.
-
Air quality permits from the Wyoming DEQ open a public comment period before approval (openair.wyo.gov).
-
Utility rate changes go through the Wyoming Public Service Commission, which takes public comment (Wyoming PSC).
In Cheyenne, city council agendas and minutes are posted at cheyennecity.org.
Do data centers get tax breaks?
Sales tax on equipment: Yes. Wyoming exempts some data center equipment from state sales tax. That includes servers, computer equipment and software, and for the largest facilities, backup power and specialized heating and cooling. To qualify, a facility has to invest at least $2 million in equipment, on top of a large investment in the building itself (Wyoming Legislature).
​
What it has cost: The Wyoming Department of Revenue estimates the exemption meant about $166 million in sales tax was not collected from 2010 through 2022 (Wyoming Department of Revenue).
​
What’s not exempt: The exemption doesn’t cover construction, property taxes, or sales tax on electricity (Wyoming Tribune Eagle). According to the Tax Foundation, Wyoming taxes data center equipment as property from the day it’s installed, while some states exempt it for 10 years or more (Tax Foundation).
​
Other incentives: States can also offer one-time incentives to attract a project. In 2012, then-Gov. Matt Mead said Wyoming offered Microsoft nearly $11 million in incentives (Cowboy State Daily).
​
Is it changing? The exemption is set in state law (Wyo. Stat. 39-15-105). In November 2025, the Legislature’s Joint Revenue Committee discussed it because the state lacks data on its effects, but no bill to change it was introduced (Wyoming Tribune Eagle).